Representation Summary:

The timescale of NEC providing housing before Marshalls is wrong.

- Marshall’s have committed to passing over a vacant site by 2030
- Supposedly the construction of NEC will start in 2028.

However, construction on a mostly “green" site (the airport), is a lot more predictable than construction on an old sewage works.

Demolition of CWWTP is going to be done after the developers take possession post 2028 (see p2-53 Anglian Water's EIA Scoping Report).

So a strong argument that housebuilding on Marshall's will start before NEC where the developer will undoubtedly find many unpleasant surprises before starting building.

Full text:

The timescale of NEC providing housing before Marshalls is wrong.

- Marshall’s have committed to passing over a vacant site by 2030
- Supposedly the construction of NEC will start in 2028.

However, construction on a mostly “green" site (the airport), is a lot more predictable than construction on an old sewage works.

Demolition of CWWTP is going to be done after the developers take possession post 2028 (see p2-53 Anglian Water's EIA Scoping Report).

So a strong argument that housebuilding on Marshall's will start before NEC where the developer will undoubtedly find many unpleasant surprises before starting building.