Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

4. Greater Cambridge Housing Trajectory and Five Year Supply Calculations

Representation ID: 168417

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

It is disappointing that the document makes no allowance for the use of the housing figure for either Council (or a combined one) which could be calculated from the use of the standard methodology for housing need: such an approach is advocated under paragraph 60 of the NPPF.

We would have expected this to be included if only to provide a potential scenario arising from an alternative approach. By our calculation the housing need for South Cambridgeshire would be 1,113 dwellings per year which is a considerable increase to the 975 dwellings per annum which is assumed within the document.

Comment

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

4. Greater Cambridge Housing Trajectory and Five Year Supply Calculations

Representation ID: 168418

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

It is concerning to note from paragraphs 4 to 6 that the Council makes no reference to the updated Planning Practice Guidance in respect of national guidance in relation to the status of combined plans (as the guidance in force when the Local Plan was adopted has now changed). We would have expected the Council to consider this given the change in policy wording.

Comment

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

3. Approach to Preparing the Greater Cambridge Housing Trajectory and Five Year Supply

Representation ID: 168419

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

It is correct to review the housing supply position in case it has altered which evidently is the case. The soundness of the Local Plan was considered against the NPPF (2012). The more recent NPPF (2019) includes a much stricter test on whether sites should be considered to be deliverable.

We have undertaken a thorough review of the alleged supply in South Cambridgeshire. We have not undertaken the same exercise for sites within Cambridge City Council due to time constraints: this should not imply in any way that we agree with the assertions for any site within Cambridge City.

There are many examples of sites which fall short of the clear evidence requirement: these include circumstances where detailed planning permissions and/or the discharge of planning conditions have not taken place; it is unclear whether developers are in place; and historic delays.

Comment

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

Appendix C: Evidence of Lead-In Times, Lapse Rates and Build Out Rates - Build Out Rates for sites of 10 dwellings or more (net)

Representation ID: 168420

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

We consider that the use of an assumed generic delivery rate for a number of sites adds considerable uncertainty as to the delivery of those sites.

Object

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

Appendix B: Assessment of Sites included in the Greater Cambridge Housing Trajectory - Allocations in the Cambridge Urban Area

Representation ID: 168421

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

Orchard Park

Lack of planning permissions on Parcel Com4 with two recent applications refused. Agent suggested Parcel L2 development not viable.

Therefore -105 dwellings.

Object

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

Appendix B: Assessment of Sites included in the Greater Cambridge Housing Trajectory - Allocations on the Cambridge Fringe

Representation ID: 168422

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

Cambridge East

Lack of Reserved Matters for Parcel 1a). No Outline planning permission for Parcel 1b). Standard trajectory figure used by the Council.

Therefore -278 dwellings.

Object

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

Appendix B: Assessment of Sites included in the Greater Cambridge Housing Trajectory - Allocations at New Settlements

Representation ID: 168423

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

Northstowe

Lack of Reserved Matters consents. Requirement for highway improvements. Landowner/housebuilder concerns about delivery.

Therefore -50 dwellings.

Object

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

Appendix B: Assessment of Sites included in the Greater Cambridge Housing Trajectory - Allocations at New Settlements

Representation ID: 168424

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

Waterbeach New Town

Lack of Reserved Matters consents on U&C scheme. Lack of Outline planning permission for RLW land and outstanding objections from statutory consultees.
Permission and application cumulatively exceed the housing allocated in the policy.

Therefore -333 dwellings.

Object

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

Appendix B: Assessment of Sites included in the Greater Cambridge Housing Trajectory - Allocations at New Settlements

Representation ID: 168425

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

Bourn Airfield New Village

Lack of Outline planning permission and outstanding objections from statutory consultees.

Therefore -250 dwellings.

Object

Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document

Appendix B: Assessment of Sites included in the Greater Cambridge Housing Trajectory - Allocations in the Rural Area

Representation ID: 168426

Received: 14/10/2019

Respondent: Abbey Properties Cambridgeshire Limited

Representation Summary:

Cambourne West

Lack of Reserved Matters consents. Agent notes legal access constraint.

Therefore -150 dwellings.

For instructions on how to use the system and make comments, please see our help guide.