Heydon Neighbourhood Plan Submission Version

Heydon Neighbourhood Plan Submission Version

Representation ID: 205557

Received: 08/02/2026

Respondent: Environment Agency

Representation Summary:

Wall repair/reinstatement at Eastern gateway to the village.

Full text:

In my opinion, of all the Community Actions listed in the Plan, the completion of work under Item 5.4.14 would have the most visual impact on the village scene and the repair/reinstatement of the part demolished wall which runs N W from the Western end of Spring pond is likely to prove the most challenging and costly. This wall has remained in its present uncared state for more than 20 years and for this reason and notwithstanding the passage of time it is important to record Heydon’s continued determination to see it reinstated.

I would like to suggest an addition as under -

Community Action 2
5.4.14 Through negotiation with relevant landowners and potential local fundraising
secure early repair and restoration of the visually important walls along the north
and south boundaries of Heydon Lane as this enters Heydon from the eastern village gateway. Emphasis of effort to be given to the repair of the part demolished wall and pier which runs N W from the western end of Spring Pond.

Support

Heydon Neighbourhood Plan Submission Version

Heydon Neighbourhood Plan Submission Version

Representation ID: 205563

Received: 10/02/2026

Respondent: Environment Agency

Representation Summary:

Please see attached East Anglian Environmental Agency formal response to Heydon NP consultation Regulation 16.

Full text:

Please see attached East Anglian Environmental Agency formal response to Heydon NP consultation Regulation 16.